Templates / Acceptance protocol
    Templates

    Acceptance protocol

    The acceptance protocol records the formal acceptance: defects noted, reservations and the start of the warranty period. A central document with significant legal consequences.

    Opens the print dialog; choose Save as PDF there.

    When to use

    At formal acceptance (VOB/B § 12, BGB § 640). Acceptance starts the warranty period and reverses the burden of proof; reservations must be declared here.

    Structure

    What it contains.

    1. HeaderProject / contract · Date and place of acceptance · Subject of acceptance (service / trade)
    2. PartiesClient (name, role) · Contractor (name, role) · Other attendees
    3. Defects notedNo. · Location / component · Defect · Deadline to remedy · Remedied on
    4. Outstanding servicesService · Date
    5. Acceptance declarationAcceptance granted: without reservation / with reservation / refused · Reservation of contractual penalty (yes / no) · Reservation regarding the defects noted · Start of the warranty period (date)
    6. SignaturesClient · Contractor
    Legal note

    Sample without warranty, not legal advice. Acceptance has far-reaching consequences (start of warranty, reversal of the burden of proof, payment falling due); reservations, especially of a contractual penalty, should be reviewed case by case.

    Structify SolutionsTEMPLATE

    Acceptance protocol

    Header

    Project / contract
    Date and place of acceptance
    Subject of acceptance (service / trade)

    Parties

    Client (name, role)Contractor (name, role)Other attendees
       
       
       
       
       

    Defects noted

    No.Location / componentDefectDeadline to remedyRemedied on
         
         
         
         
         

    Outstanding services

    ServiceDate
      
      
      
      
      

    Acceptance declaration

    Acceptance granted: without reservation / with reservation / refused
    Reservation of contractual penalty (yes / no)
    Reservation regarding the defects noted
    Start of the warranty period (date)

    Signatures

    Client
    Contractor

    Structure template by Structify, to fill in or use digitally at structify.solutions · Sample without warranty, not legal advice.

    Digital with Structify

    Frequently asked questions

    With acceptance the warranty period starts, the burden of proof reverses and payment falls due. Defects noted and any reservation of the contractual penalty must be documented in the protocol.

    An inspection is ongoing monitoring; acceptance is the legal approval of the service as essentially in line with the contract. Both are recorded, but they have different legal consequences.