    Design changes: adjusting fees under § 10 HOAI

    AI-generated image: Design changes: adjusting fees under § 10 HOAI

    Design changes and HOAI fees: how firms agree, document and bill extra work under § 10 HOAI 2021 and §§ 650b, 650q of the German Civil Code.

    After the design planning is finished, the client decides to add a second apartment in the attic. The firm redraws floor plans and sections, coordinates again with the structural design and updates the cost calculation. In the end, only the original fee is billed. If you do not agree on and document the fee for a design change under the HOAI promptly, you give away work you have already done.

    Why extra work from design changes goes unpaid

    The pattern is the same in many firms. The change request arrives in passing: in a site meeting, on the phone or as a message in a private messaging app. The team responds quickly because nobody wants to put the schedule at risk. The fee is something to discuss later.

    Later often means the final invoice. There, the extra items meet a client who remembers things differently:

    • Disputed cause: The change was supposedly suggested by the firm itself.
    • Disputed scope: The redesign was supposedly part of the basic services already commissioned.
    • Missing reference: Nobody can say which plan revision applied before the change and which applied after it.

    The result is lost fees, often combined with a dispute at the end of a project in which the cooperation had actually gone well. The risk grows with every service phase that builds on the changed design.

    What § 10 HOAI 2021 covers

    The HOAI is the German fee scale for architects and engineers. In its 2021 version, § 10 governs how the fee is calculated when client and contractor agree to change the scope of services during the term of the contract. The provision distinguishes two cases. Both concern basic services (Grundleistungen), meaning the services generally required to properly perform a commission (§ 3 (2) HOAI).

    Paragraph 1: chargeable costs change

    Chargeable costs are the share of the costs under DIN 276, the German standard for building costs, from which the fee for basic services is calculated. If the agreed change alters the chargeable costs, areas or units of account, the basis for calculating the fee for the basic services required as a result of the changed scope must be adjusted by an agreement in text form (§ 10 (1) HOAI 2021). In the attic example, the chargeable costs rise. The fee for the affected services is then calculated on the new basis.

    Paragraph 2: basic services are repeated

    If the chargeable costs stay the same but the firm has to perform basic services again that it has already delivered, the fee for this repetition must be agreed in text form according to its share of the relevant service phase (§ 10 (2) HOAI 2021). Service phases are the nine stages into which the HOAI divides planning and supervision services, each carrying a percentage of the total fee.

    Example: The fee for the basic services for a building is around EUR 80,000. Design planning (service phase 3) is weighted at 15 percent for buildings under § 34 HOAI, which is around EUR 12,000. If roughly half of the design planning has to be redone after a change request, an agreement in the range of around EUR 6,000 is a reasonable starting point. These figures are a sample calculation, not fee advice. You can estimate the starting values with the HOAI calculator.

    Text form under § 126b of the German Civil Code (BGB) means a legible declaration on a durable medium that names the person making it. An email is sufficient; a handwritten signature is not required.

    Right to order changes and fees under §§ 650q, 650b and 650c BGB

    § 10 HOAI requires an agreement. If none is reached, the construction contract rules of the BGB apply. § 650q (1) BGB makes, among others, § 650b BGB applicable to contracts with architects and engineers. The process usually looks like this:

    1. Change request: The client requests a change to the agreed design outcome or a change that is necessary to achieve that outcome.
    2. Negotiation: Both sides seek agreement on the change and on the additional or reduced fee. The firm usually submits an offer.
    3. Order: If no agreement is reached within 30 days of receipt of the change request, the client may order the change in text form (§ 650b (2) BGB).
    4. Fee: Under § 650q (2) BGB, the HOAI calculation rules apply to services covered by the HOAI, including § 10 HOAI. For any other additional or reduced effort, the fee can be freely agreed. Without an agreement, § 650c BGB applies accordingly: the costs actually required plus reasonable surcharges for general overheads, risk and profit.

    What this means in practice: an order replaces the agreement on the service, not the proof of effort. If you have to bill under § 650c BGB, you need reliable records of which hours and costs relate to the change.

    Drawing the line: change, optimization or special service

    Not every redesign justifies an additional fee. Three distinctions come up again and again in disputes.

    • Variants within the basic service: In preliminary planning, examining and evaluating variants under the same requirements is a basic service (Annex 10 to the HOAI). If the client changes the requirements themselves, such as the space program, use, standard or budget, that strongly suggests a change within the meaning of § 10 HOAI.
    • Correcting your own errors: If the firm has to rework the design because its own planning was deficient, there is no claim to an additional fee.
    • Special services: Special services (Besondere Leistungen) are services that go beyond basic services or replace them. Their fee can be freely agreed under § 3 (3) HOAI. One example from preliminary planning is examining alternative approaches under different requirements. Here, § 10 HOAI does not apply; a separate agreement does, ideally concluded before the work starts.

    Whether a change caused by permit conditions or by revised specialist planning is paid depends on the contract and the individual case. A clear fee agreement at the start of the project that expressly covers changes and repetitions takes the edge off many of these questions. How the basic fee is built from fee zone, fee rate and service phases is explained in the article on calculating HOAI fees.

    Documentation: what, when, at whose request, which plan revision

    A fee claim arising from a design change is only as strong as its records. For every change, record four points:

    • What was changed, with reference to the building element, floor or plan content?
    • When was the request made, and when was it confirmed or ordered?
    • At whose request was the change made: client, user, authority or specialist planners?
    • Which plan revision applied before, which applies after, and which service phases are affected?

    Then there is the effort: affected drawings, coordination and hours, ideally recorded as you go rather than estimated afterward. Announce the additional fee before you start redesigning, and get the change and the fee confirmed in text form. How clear plan revisions help is described in the article on managing plan revisions on site. How a meeting turns into a reliable record is shown in the article on the inspection report.

    The limits are clear: neither a template nor software decides whether a change must be paid for. That assessment is made by the firm, and in disputed cases together with legal counsel.

    Checklist

    • Record every change request immediately, with date, originator and content.
    • Check whether the chargeable costs change (§ 10 (1) HOAI) or basic services are repeated (§ 10 (2) HOAI).
    • Determine whether the work is a variant within the basic service, an error correction or a special service.
    • Name the affected service phases and their share of the fee.
    • Announce the additional fee and submit an offer before redesigning starts.
    • Obtain an agreement in text form; if no agreement is reached, keep the 30-day period under § 650b (2) BGB in view.
    • Label plan revisions before and after the change clearly.
    • Record effort continuously, separating the change from the original commission.
    • Bill agreed changes promptly, in the next interim invoice and later in the final invoice.

    Frequently asked questions

    Does the agreement on the change fee need to be signed?

    No. § 10 HOAI 2021 requires text form, and text form under § 126b BGB does not require a handwritten signature. An email that names the change and the fee and is confirmed by the client usually meets this requirement.

    What applies if the client orders the change but no fee is agreed?

    Under § 650q (2) BGB, the fee for services within the scope of the HOAI follows its calculation rules. For any effort beyond that, § 650c BGB applies accordingly if there is no agreement, meaning the costs actually required plus reasonable surcharges.

    Are variants in preliminary planning paid separately?

    Variants under the same requirements are usually part of the basic services of service phase 2 and are covered by the basic fee. Alternative approaches under different requirements, by contrast, are a special service whose fee is freely agreed.

    Can a design change still be billed in the final invoice?

    An existing claim is usually not lost simply because it first appears in the final invoice. However, the longer ago the change was made, the harder it is to prove who caused it and what effort it required. Under § 15 (1) HOAI 2021, the fee becomes due upon acceptance of the services and submission of a verifiable final fee invoice.

    Conclusion

    Extra work from design changes often goes unbilled not because of the legal position, but because of missing records and conversations held too late. § 10 HOAI 2021 and §§ 650b and 650q BGB provide a clear framework: recognize the change, classify it, agree the fee in text form and document plan revisions properly. Structify is software for digital construction documentation and connects fees and billing under HOAI 2021 with site inspections and reports in one project. Speech is automatically turned into a report, so change requests from meetings are recorded with date and participants. If you would like to see how this looks on your project, book a short online demo.