Missing drawings, a late preceding trade, a site stop because a permit is still outstanding: when a project stalls, the question is whether the contractor gets more time and who bears the extra costs. The VOB/B, the standard German terms for construction contracts, answers both mainly in Section 6, supplemented by Section 642 of the German Civil Code (BGB) and, for ordered changes, by Section 2(5) VOB/B. This article gives an overview and is not legal advice for the individual case.
Prerequisite: the notice of hindrance
Every extension of time in a VOB/B contract starts with the notice of hindrance. If the contractor considers itself hindered in the proper execution of the work, it must notify the client in writing without undue delay under Section 6(1) sentence 1 VOB/B. Without notice, the hindering circumstances are only taken into account if the client obviously knew of the fact and its hindering effect (sentence 2). Its structure is explained in the article on the notice of hindrance under VOB/B; there is also a template.
Extension of the execution periods under Section 6(2) and (4) VOB/B
The agreed execution periods (Section 5 VOB/B) are extended under Section 6(2) number 1 VOB/B to the extent the hindrance is caused
- by a circumstance within the client's sphere of risk,
- by a strike or a lockout ordered by the employers' professional association in the contractor's business or in a business working directly for it,
- by force majeure or other circumstances the contractor could not avert.
Weather conditions during the execution period that normally had to be expected when the bid was submitted are not a hindrance under Section 6(2) number 2 VOB/B.
The duration is set out in Section 6(4) VOB/B: the duration of the hindrance plus a surcharge for resuming the work and for any shift into a less favourable season. Because the relevant date moves, the extension also affects an agreed contractual penalty. If the schedule is thrown into disorder as a whole by hindrances or orders, a contractual penalty tied to fixed dates may, according to case law, even lose its basis.
At the same time, under Section 6(3) VOB/B the contractor must do everything that can reasonably be expected to allow work to continue, and must resume promptly once the hindrance ends. If an interruption lasts longer than three months, either party may, once that period has expired, terminate the contract in writing under Section 6(7) VOB/B (see terminating the construction contract).
Money: damages and compensation
Section 6(6) VOB/B provides two routes.
Damages under Section 6(6) sentence 1 VOB/B. If one party is responsible for the hindering circumstances, the other party is entitled to compensation for the damage demonstrably incurred, but to lost profit only in the case of intent or gross negligence. According to case law, this claim of the contractor also requires that the hindrance was notified under Section 6(1) VOB/B or was obvious. The claim requires fault and works both ways: the client can also assert it if the contractor is responsible for the delay (see also Section 5(4) VOB/B). If the VOB/B is not incorporated in its entirety without substantive deviations, or is used against a consumer, its clauses, including the limitation on lost profit, are reviewed individually as standard terms (Section 310(1) sentences 1 and 3, Section 310(3) number 1 BGB); this review only protects the user's counterparty.
Compensation under Section 642 BGB via Section 6(6) sentence 2 VOB/B. Irrespective of fault, the contractor's claim to reasonable compensation under Section 642 BGB remains unaffected, provided the notice under Section 6(1) sentence 1 VOB/B was given or the hindrance was obvious. Section 642 BGB requires that an act of the client is necessary to produce the work and that the client, by failing to perform it, is in default of acceptance, for example because the construction area is not available or approved drawings are missing. The contractor must also be willing and able to perform and have offered its performance (Sections 294 to 297 BGB); a verbal offer suffices here under Section 295 BGB and can be combined with the notice of hindrance. Under Section 642(2) BGB, the amount is assessed on the one hand on the duration of the default and the agreed remuneration, and on the other hand on what the contractor saves in expenses or can earn by using its workforce elsewhere. According to the case law of the Federal Court of Justice, the compensation relates to the period of default of acceptance; extra costs arising only afterwards, such as higher wage or material costs, are not automatically covered.
Distinction: additional remuneration under Section 2(5) VOB/B
Not every change in construction time is a hindrance. If the client itself orders something that changes the basis of the price, such as a change to the design or to the sequence of execution, a new price taking the additional or reduced costs into account must be agreed under Section 2(5) VOB/B. This is a claim to remuneration without any fault requirement, not damages. Whether and how far the client may unilaterally order changes to the construction time is, however, disputed. For the BGB construction contract, see the article on the right to order changes under Section 650b BGB. Time-related extra costs of an order, such as site overheads and equipment standby, belong in the change order under Section 2(5) VOB/B; the extension of the execution period is governed by Section 6 VOB/B. Order and disruption must therefore be kept apart.
Proof: a presentation based on the construction process
Claims for construction time most often fail at the presentation stage. According to case law, an abstract comparison between planned and actual progress is not enough. For each hindrance, the contractor must show specifically when it occurred, how long it lasted, which work it affected and how it affected the further construction process. The hindrance itself must be specifically proven; for its effects on the further construction process and for the amount of damage, case law allows the court to estimate under Section 287 of the Code of Civil Procedure (ZPO), provided sufficient underlying facts are presented.
The basis is created on site:
- Construction schedule: the updated planned sequence with dependencies is the yardstick for every deviation.
- Site diary: daily entries on staff, equipment, weather, progress and disruptions prove the start and end of a hindrance (see site diary: obligation and content).
- Photo documentation: dated photos show the condition of the construction area, for example an unfinished preceding trade.
- Site meeting minutes and correspondence: receipt of drawings, approvals, notices and the reporting of the end of a hindrance belong in a traceable record.
Delay by the preceding contractor
If the preceding contractor has not finished, attribution is difficult. According to case law, the preceding contractor is generally not the client's vicarious agent in relation to the following contractor; damages under Section 6(6) sentence 1 VOB/B are therefore often excluded unless the client has itself assumed a corresponding obligation. Compensation under Section 642 BGB may, however, come into consideration, because providing a buildable construction area is part of the client's cooperation. The extension of time is usually less problematic, because the delay originates from the client's sphere of risk. Where a general contractor has awarded the trades itself, this applies accordingly between it and its subcontractors; claims of the following subcontractor are then directed against the general contractor, not the building owner. Towards the building owner, the general contractor itself answers for delays by its subcontractors.
BGB construction contract without VOB/B
Without the VOB/B, there is no express rule on extending deadlines like Section 6(2) and (4). However, the contractor is not in default as long as it is not responsible for the delay (Section 286(4) BGB), for example because the client fails to perform a necessary act of cooperation; according to case law, the execution periods are then extended reasonably, based on Section 6(2) and (4) VOB/B. Compensation under Section 642 BGB applies directly. Under Section 643 BGB the contractor can set a reasonable deadline to make up for the cooperation and declare termination in case it expires without result; the contract is then deemed cancelled. Damages may be considered under Sections 280 et seq. BGB, for delay via Section 286 BGB, if an obligation was breached and the obligor is responsible for it. Whether the client's cooperation is a genuine obligation or merely an incumbency depends on the contract. A written notice of hindrance makes proof easier here too.
Role of planners
For architects and engineers, the topic is part of site supervision in service phase 8. For buildings and interiors, Annex 10.1 of the HOAI, the German fee structure for architects and engineers, includes drawing up, updating and monitoring a schedule (bar chart) and documenting the construction process, for example in a site diary. Both are the central evidence for or against claims for construction time.
The planner is often the cause itself: if detailed drawings arrive late, the hindrance lies within the client's sphere of risk. According to case law, the client may have to accept its planner's fault being attributed to it in relation to the executing contractor, to the extent the client owes that contractor the drawings.
Practical checklist
- Notify the hindrance in writing immediately: cause, work affected, expected consequences.
- Record start and end in the site diary, report the resumption.
- Separate orders from disruptions and treat them as a change order under Section 2(5) VOB/B.
- Record costs separately: idle staff and equipment, site overheads, extra costs of resumption.
Frequently asked questions
Is the construction time automatically extended by the duration of the hindrance?
Not automatically, and not only by that duration. Under Section 6(4) VOB/B a surcharge for resumption and any less favourable season is added. It requires a circumstance under Section 6(2) VOB/B and notice or obviousness.
Does the claim under Section 642 BGB require fault on the part of the client?
No. It is linked to default of acceptance, that is, a necessary act of cooperation that was not performed. In a VOB/B contract, however, the hindrance must have been notified or obvious.
Is a comparison of the planned and actual schedule sufficient as proof?
According to case law, generally not. A specific presentation of each hindrance and its effect, based on the construction process, is required.
Is the architect liable if drawings arrive late?
It can be liable to the client if it culpably breaches its obligations to deliver drawings. The executing contractor generally turns to the client, which can take recourse against the planner.
Conclusion
Claims for construction time rest on three elements: a timely notice, the right legal basis and proof that reflects the construction process specifically. The construction process is documented in Structify in the site diary with daily reports; you record site inspections by voice, photo and note, also offline on iPhone, iPad and Android, and manage change orders in the same project. Structify is hosted in Germany and free of charge for external parties per project. A demo shows how a construction process can be traced with it.